by daniel | Nov 22, 2019 | Project Update
The Lake Harbour Drive Extension project in Ridgeland, MS is on schedule and approaching the half-way mark. To date, the bridge deck pours are underway, the roadway subgrade is almost complete, and the railroad box culvert and pedestrian box culvert have been... by daniel | Oct 3, 2019 | News, Project Update
WEI/IMS, II LLC, are proud to announce the opening of Hinds Parkway Segment Two. Construction began in July 2017 and finished ahead of schedule in August 2019. County officials held a ribbon-cutting this morning at the section of the parkway that includes... by daniel | Sep 19, 2019 | News, Project Update
RIDGELAND — Work on the $22 million Lake Harbour Drive extension is slightly ahead of schedule, city officials said this week, as progress is clearly visible to those driving throughout the area. Recently, beams were installed for the I-55 overpass closing the I-55... by daniel | Aug 19, 2019 | News, Project Update
Ridgeland officials broke ground on a 25-acre site Friday. Waggoner has been involved from the beginning with design and planning. The plans call for an energy-efficient building and the city will allow some retail space in the complex. Completion is slated for late... by daniel | Jul 1, 2019 | News, Project Update
Check out this awesome drone footage of the Lake Harbour Drive Extension...